Small Generator Interconnection Process
The Maine Public Utilities Commission has Chapter 324, Small Generator Interconnection Procedures which lists the procedures for interconnecting to Bangor Hydro's distribution system.
Interconnection Procedures:
- Complete Interconnection Application
- Level 1 Interconnection Application for Certified, Inverter-Based Generating Facilities Not Greater than 10 kW
- Level 2, Level 3 and Level 4 Interconnection Application where:
- Level 2 - For certified generating facilities that pass certain specified screens and have a power rating of two megawatts (2MW) or less. The T&D Utility shall adopt procedures in accordance with § 9 for this level of review.
- Level 3 - For certified generating facilities that: (a) pass certain specified screens; (b) do not export power beyond the Point of Common Coupling; and (c) have a power rating of ten megawatts (10MW) or less. The T&D Utility shall adopt procedures in accordance with § 10 for this level of review.
- Level 4 - For all generating facilities that do not qualify for Level 1, Level 2 or Level 3 interconnection review processes, and are not subject to the jurisdiction of FERC. The T&D Utility shall adopt procedures in accordance with § 11 for this level of review.
- Remit Interconnection Application Fee as set by the MPUC under Chapter 324 § 8.G., 9.I., 10.H., and 11.U.
| Level |
Nameplate Rating |
Application Fee |
| Level 1 |
Inverter-Based Generators Not Greater than 10KW |
$50 |
| Level 2 |
Generators Not Greater than 2MW |
$50 plus $1.00/KW |
| Level 3 |
Non-Exporting Generators Not Greater than 10MW |
$100 plus $1.50/KW |
| Level 4 |
All Generators Not Subject to FERC Jurisdiction |
$100 plus $2.00/KW ($400 max) |
- Execute Interconnection Agreement
- Level 1 Interconnection Agreement
- Level 2, 3, or 4 Interconnection Agreement
- Execute Net Energy Billing Agreement (if applicable)
- Completion of Facility Inspection by a Bangor Hydro Power System Technician.
Bangor Hydro MUST inspect the generating facility PRIOR to the system going live.
Additional Documents related to Interconnection/Net Energy Billing:
If you have any questions about the Interconnection Process, please contact our Net Billing Coordinator:
Phone: (207) 973-2510
Toll free: (855) 770-3985